Project Gallery

Hilton Hotel Cleveland Convention Center
Hilton Hotel Cleveland Convention Center
Hilton Hotel Cleveland Convention Center
Hilton Hotel Cleveland Convention Center

Market
    Commercial & Office
Project Size
  • 612,500 sq. ft.
Architect
  • Cooper Cary, Van Aukin Akins Architects
Contractor
  • Turner Construction Company

Hilton Convention Center Hotel

Hilton Worldwide

Cleveland, Ohio

Donley's served as the concrete contractor to Turner Construction, on the new Hilton Cleveland Convention Center Hotel, located in downtown Cleveland.

The hotel was completed in time for the 2016 Republican National Convention, held July 18-21, 2016.  

Donley's scope of work included:   

  • Structural concrete design-assist services
  • Foundations
  • Basement walls
  • Elevator core walls
  • Podium slab on metal decks
  • Podium beam & slab decks
  • Tower flat plate post tensioned decks
  • Tower structural stairs