New Year Brings New Projects to Virginia Market

Donley’s is heading into the new year with new projects! Read about our completed and in-progress projects that are continuing our growth in the Virginia market into 2023.

UVA Alderman Library

Construction Manager: Skanska

Project Size: 171,000 SQFT

Concrete: 11,550 CY

Status: Completed

  • UVA Alderman Library - Donley's

UVA Darden Inn

Construction Manager: W.M. Jordan

Project Size: 233,000 SQFT

Concrete: 11,750 CY

Status: Completed

  • UVA Darden Inn - Donley's

700 Semmes

Construction Manager: Clancy & Theys Construction Company

Project Size: 155,600 SQFT

Concrete: 5,760 CY

Status: Completed

  • 700 Semmes - Donley's

Greystar Scott’s Addition

Construction Manager: Clancy & Theys Construction Company

Project Size: 268,200 SQFT

Concrete: 12,000 CY

Status: Completed

  • Greystar Scott's Addition - Donley's

NOVEL Scott’s Addition

Construction Manager: Clancy & Theys Construction Company

Project Size: 97,500 SQFT

Concrete: 3,875 CY

Status: In-Progress

  • NOVEL Scott's Addition - Donley's

Pinecrest Student Housing 

Construction Manager: Rycon Construction 

Project Size: 325,000 SQFT

Concrete: 8,450 CY

Status: In-Progress

  • Pinecrest Student Housing - Donley's

Dominion Energy – Technical Support Building & High-Voltage Lab

Construction Manager: Barton Malow 

Project Size: 94,800 SQFT

Concrete: 6,850 CY

Status: In-Progress

The Eddy Apartments

Construction Manager: Hourigan Group

Project Size: 77,000 SQFT

Concrete: 3,200 CY

Status: In-Progress

  • The Eddy Apartments - Donley's

New Role for George Esner

George Esner has spent the last two years helping execute Donley’s Concrete Group VA’s Move Forward plan – shifting us from a construction manager to a self-perform concrete market leader.  During that time, he has helped to solidify our operations and build a strong team in Virginia. George has now returned to Northeast Ohio and will continue as the Director of Operations, but with a refocus in his position to touch all business units. He will be a liaison between operations and functional departments to ensure corporate processes are effective and efficient.

Specifically, George will support budgeting, job cost processes, and other operational accounting processes. He will also continue to be a developmental resource for all Donley’s operational personnel utilizing his passion for training and team building. George’s 18+ years of experience with Donley’s, complemented by his upcoming completion of Ohio University’s MBA program, gives George the perfect background for his new responsibilities.

Please congratulate George on his past successes and new role at Donley’s.

David Coleman Promoted to Sr. Project Manager

Please join us in congratulating David Coleman on his promotion to Senior Project Manager.

David joined Donley’s as a Co-Op back in May of 2010.  He came on board full-time as a Project Engineer in construction management a few months later.  In 2014, he was promoted to Project Manager.  Over the next 3 years, David managed several higher education and parking deck projects.  In 2017, Donley’s began to focus on growing our concrete self-perform business in the Virginia market.  At this point, David transitioned from the CM group and began working as a Project Manager within Donley’s Concrete Group.  After managing concrete projects for another two years, David was promoted to Project Controls Manager and took the lead in managing our ISO certification process. He focused his efforts on fine-tuning our processes and looked for ways to eliminate waste across all concrete operations throughout the south east. During that time, David also took on the responsibility of wrapping up multiple CM projects while continuing his role in project controls and managing structural concrete projects.

We look forward to David’s continued leadership as we become the premier concrete contractor in the Virginia market.  Congratulations David!