801 Rockwell Avenue Parking Deck
Working with the owner and Engineer, we devised a restoration plan to add another 15 to 20 years of serviceable life to the structure for ¼ of the cost to replace it. Donley’s Restoration Group worked with construction engineers, Barber & Hoffman, to provide:
- Full and partial slab repair
- Full joist replacement
- Beam and column repair
- Curb removal
- Membrane removal and new membrane application
- Drain replacement
- Supplemental reinforcing steel
- Full deck replacement
- Construction of a new ramp reaching the top floor
Project Duration: 15 months