Cross Generating Foundations

This project includes the addition of a wastewater treatment facility to an existing 2,390 MW coal fired generating facility owned and operated by Santee Cooper. This facility will enable the plant to treat coal ash water to meet more stringent EPA regulations.

DCG is providing 36” deep foundations with pits up to 16 feet deep, slab on grade, 26 foot high push walls, piers and beams, curbs, tank and pump pads, topping slabs and trench infill for over two dozen separate structures.  DCG will pour nearly 33,000 cubic yards of concrete on this project.

Expected to be completed by April 2018.

Processing Plant & Wastewater Treatment Facility

In January 2017, working with Choate Construction / Raleigh as construction manager, DCG finished the Sanderson Farms processing plant and wastewater treatment facility in St.Pauls, N.C. The $8M contract included a turnkey concrete package, consisting of large spread footings, grade beams, pits and trenches for the processing facility, 285,000 sq. ft. of slab on grade and elevated slabs, including 400,000 sq. ft. of exterior concrete paving. The project had 21,000 cubic yards of concrete placed out of an onsite concrete batch plant. Donley’s Concrete Group’s portion of the project was completed in 11 months and is DCG’s second processing facility for Sanderson Farms.

Tool Expansion

Donley’s has been awarded the Spirit AeroSystems Tool Expansion in North Carolina.  The facility manufactures miscellaneous parts for the aeronautical community.

The scope of work for the project includes:

  • turnkey concrete construction
  • pile caps
  • grade beams
  • tie beams
  • loading docks
  • stone base
  • high floor tolerance slab on grade, including misc. site concrete

“BMCD and Spirit are also very thankful the goal was met and was done safely even in the inclement weather.  Donley’s continued working through the rain which was acknowledged by Spirit in addition to our team.  The efforts are very much appreciated and BMCD and Spirit look forward to working with Donley’s team in the future.”

Cree NCE Expansion

Donley’s Concrete Group served as concrete contractor to DPR Construction on a facility expansion project for Cree, Inc. located in Durham, North Carolina.

Cree, Inc. is a market-leading innovator of lighting-class LED’s, LED Lighting, and semiconductor solutions for wireless and power applications.

Donley’s scope of work included:

  • light demolition of existing mud slabs
  • installation of typical pier foundations, wall footings, and retaining walls
  • slab-on-grade consisting of 90,000 sq. ft. of 14″ thick mat slab
  • 80,000 sq. ft. of cast-in-place elevated flat plate decks
  • 80,000 sq. ft. of elevated composite decks on structural steel

Biotechnology Growth Environment & Greenhouse

Syngenta Biotechnology’s Growth Environment 1 is a 130,000 sq. ft. testing facility for soil and plants. The building includes a 41,000 sq. ft. insulated glass greenhouse constructed above a 64,000 sq. ft. cast-in-place basement.

Performing turnkey concrete construction services, Donley’s Concrete Group excavated the heavy foundations and placed the pile caps, columns, shear walls, and 2 ft. thick cast-in-place pan deck. All placements of the elevated decks were made by hand-screeding and non-mechanical methods in order to accommodate the required tolerance of Ff 50.