Canton Cultural Center Parking Deck

Canton Cultural Center Parking Deck

The Cultural Center for the Arts in Canton, Ohio is an award-winning designed complex set on more than nine acres near the downtown business and arts districts. Donley’s Concrete Group performed 30,000 sq. ft.of concrete deck repairs and traffic membrane application overtop of the Canton Cultural Center’s finished 330,000 sq. ft. arts facility while it was open and actively being used. The two months of renovations were completed in June of 2017.

Acacia On The Green

Acacia On The Green Garage Repairs

During the project’s seven-month schedule at this condominium community in Lyndhurst, Ohio, various structural concrete and waterproofing repairs were made across Acacia on the Green’s elevated parking deck and below grade slab-on-grade. This parking deck was in use by the public during the project, which included several $100,000.00 + cars parked in the deck during construction. With rigorous planning and safety measures, no vehicles were damaged. The cost of the project was over $1.6 million and completed in February 2016.

Progressive Field

Progressive Field Topping Slab Replacements

The renovations for Progressive Field Topping Slab Replacements consisted of concrete removal, waterproofing, and replacement of approximately 20,000 sq. ft. of elevated structural deck topping slabs. Most of the work occurred during the Cleveland Indians’ off-season. Donley’s also took advantage of the Indians’ schedule in the summer to remove, waterproof, and replace approximately 2,000 sq. ft. of concrete while the team was out of town. Donley’s is currently off site, but will return in the fall of 2017 to complete the project.

Huntington Parking Garage

Huntington Parking Garage

Donley’s Restoration Group is serving as Design Assist Subcontractor to repair and upgrade Cuyahoga County’s 40-year-old parking structure, Huntington Parking Garage, located at Lakeside Avenue and West 3rd Street in downtown Cleveland. The 1,100-space, 4-level garage provides parking for the Justice Center, Cuyahoga County Courthouse, Cleveland Convention Center, and the new Hilton Cleveland Downtown Hotel.

Scope includes extensive structural concrete repairs, waterproofing, and various upgrades to meet ADA compliance standards.  Full depth beam replacement occurred 50 ft. above grade and was shored during demolition and replaced after, to allow parking operations to continue. The Huntington Parking Garage project is scheduled for completion in late summer 2017. The contract is valued at over $10 million, making it DRG’s largest project to date.

James A. Garfield Memorial Restoration

James A. Garfield Memorial Restoration

The James A. Garfield Memorial is a historical highlight in Lake View Cemetery, dating back to
1885. Over 100 years later, time had taken its toll on this Cleveland Memorial.
The foundation of the 180 ft structure needed to be repaired and supported.

The James A. Garfield Memorial Restoration involved multiple phases as part of the restoration plan
starting with the restoration of the memorial’s deteriorating foundation and
first level. The restoration involved:

 

  • Demolition
    of the existing concrete slab, and previously installed steel shoring

  • Stabilization
    of the Structure prior to demo operations

  • Installation
    of new concrete foundations, columns, and beams

  • Tuck-pointing
    of the existing crypt walls

  • Relocation
    of the existing boiler

  • Installation
    of new underground plumbing, connection to the existing plaza drains