Working with the owner and Engineer, we devised a restoration plan to add another 15 to 20 years of serviceable life to the structure for ¼ of the cost to replace it. Donley’s Restoration Group worked with construction engineers, Barber & Hoffman, to provide:

▪Full and partial slab repair
▪Full joist replacement
▪Beam and column repair
▪Curb removal
▪Membrane removal and new membrane application
▪Drain replacement
▪Supplemental reinforcing steel
▪Full deck replacement
▪Construction of a new ramp reaching the top floor

Project Duration: 15 months