Donley’s project team switched over the gas supply at Akron Summa Hospital late on March 24 and into the morning of the 25th.  This has been an ongoing effort for a few months to establish a step-by-step process to safely perform the work, shut down a few services, and switch the Boiler House over to Fuel Oil until purges were complete. The plan was well executed, and the team was flexible enough to re-prioritize on the fly to handle unexpected rain. We are looking forward to teaming up with Shook Construction on this great project which is breaking ground on May 15th.